June 2020
24 piles were made for the house of section # 4 The pile frames of section 4 were taken to the construction site in full
foto
foto
foto
foto
foto
foto
foto
July 2020
Закончены работы по устройству ограждения котлована 4 секции. Забито 110 из 158 свай секции 4. Начать работы по разработке котлована 3й секции. Планируется в течение 3-4 недель завоз и монтаж башенного крана 4 секции
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
August 2020
Начаты работы по устройству свай секции 3 Завершено устройство бетонной подготовки для фундаментной плиты секции 4 Выполнено бетонирование плиты фундамента башенного крана # 1
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
September 2020
Выполняются работы по армированию фундаментной плиты секции №4 Завершены работы по разработке котлована части подземного паркинга в створах секций №3 и №4 Выполнена щебеночная подготовка на секции №3 Завершено обустройство бетонной подготовки для фундаментной плиты №3 Завершено вязкую каркаса и обустройство опалубки фундаментной плиты секции №4 Осуществляется прием бетонной смеси в плиту фундамента секции №4, общим объемом 750 м³
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
October 2020
Выполняются работы по армированию фундаментной плиты секции №4 Завершены работы по разработке котлована частей подземного паркинга в створах секций №3 и №4 Выполнено щебеночное подготовку на секции №3 Завершено обустройство бетонной подготовки для фундаментной плиты №3 Завершена вязка каркаса и обустройство опалубки фундаментной плиты секции №4 Осуществляется прием бетонной смеси в плиту фундамента секции №4, общим объемом 750 м³
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
November 2020
Section 2: Water lowering measures in the area of ​​the elevator pit have been completed Work has begun on the reinforcement of the foundation slab Section 3: Work is underway on the arrangement of vertical parking elements and a set of floor slabs Section 4: Work is underway on the arrangement of the floor slab of the 4th floor at the mark +8800
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
December 2020
Section 4 - the formwork of the 7th floor floor slab is being assembled at the mark +12100, ventilation units up to the mark +12 100 have been installed;
Section 3 - reinforcement of vertical elements of the 3rd floor is performed at the mark +5 500;
Section 2 - reinforcement of vertical parking elements is performed at the mark -3400;
Other works - concreting of the foundation slab of the parking lot outside the building spot of the sections was performed.
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
January 2021
SECTION 4 - reinforcement of vertical elements of the 8th floor is performed at the mark + 18 700, grinding of monolithic structures and preparation for brickwork of walls continues, works on arrangement of wall formwork of part of underground parking outside the spot of construction of sections are performed;
SECTION 3- reinforcement of vertical elements of the 5th floor at the mark +8 800 and dismantling of the formwork of the floor slab, ceiling height - 6 m
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
February 2021
Work has begun on laying the brick walls of section 3
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
March 2021
Section 1. In March, work will begin on the development of the pit: the arrangement of the pile field, etc.
In 2 sections works on the device of reinforced concrete vertical elements of the atypical first floor are carried out. The term of performance of these works makes more than 3 weeks, after all height of a floor - 5600 mm. Also on this floor there is a built-in transformer substation
Section 3. Works on arrangement of vertical elements of the 8th floor are carried out
Section 4. Works on arrangement of a plate of overlapping of the 10th floor are carried out . Work on the installation of ventilation units, flight of stairs, platforms (production gap is 2 floors) is planned. Work is underway on the arrangement of external and internal walls and partitions on the 4th and 5th floors. From May 1, the process of arranging internal engineering networks will begin
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
April 2021
SECTION 1 - work begins on the arrangement of the foundation piles
SECTION 2 - a set of floor slabs at the mark +5500
SECTION 3 - vertical elements of the 9th floor at the mark +28 000
OTHER WORKS: Masonry work has begun in the basement. The level of the tower crane №2 is raised
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
May 2021
Section 1 - completed work on the arrangement of foundation piles. The foundation for the tower crane has been prepared. Compacted soils under the foundation slab.
Section 2 - a set of floor slabs is made at the mark +8800 - office floor.
Section 3 - vertical elements are mounted at the mark +37 000. Work on masonry of external walls and partitions from the 3rd to the 6th floor inclusive continues.
Section 4 - a set of floor slabs is made at the mark of +46 000. Works on masonry of external walls and partitions from the 3rd to the 7th floor inclusive are carried out.
Other works: Work on masonry walls in the basement and on the technical floor has been completed.
foto
foto
foto
foto
June 2021
Section 1 - Concrete preparation for the foundation slab has been made. Reinforcement of the foundation slab begins.
Section 2 - A set of floor slabs at elevation +15 400 is in progress. Filling of vertical elements is continued at elevation +12 100
Section 3 — The floor slab is being concreted at elevation +43 000.
Section 4 - Concreting of vertical elements at elevation +49,000 is in progress. Progress in brickwork has reached the level of the 11th floor
We also remind that the third tower crane was installed on the construction site last month.
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
July 2021
Section 1 - Reinforcement of the floor slab -1 floor
continues Section 2 - Reinforcement and concreting of vertical structures continues according to the schedule.
Section 3 - Brickwork is carried out at the level of the 9th floor and in the coming days the workers will move to the 10th!
Section 4 - Began wiring of water supply, heating, and installation of electric risers.
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
August 2021
Section 1 - Wall waterproofing is in progress. Concreting of the vertical is in progress at elevation +2200.
Section 2 - Reinforcement of the floor slab is in progress at an elevation of + 25,000.
Section 3 - Formwork is being set at elevation +58 000. ⠀⠀
Section 4 - Concreting of vertical elements at elevation +67,000 is in progress. Brickwork progress reached 16th floor
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
September 2021
Section 1 - Concreting of a vertical on a mark +5500 is carried out
Section 2 - We moved to concreting and reinforcement of vertical structures at + 25,000
Section 3 - Reinforcement of the vertical at the mark +64 000. Reinforcement of the floor slab at the mark of +67 000. The brickwork is at the level of the 13th floor
Section 4 -Concreting of vertical elements at a mark of +70 000 is carried out. Another floor slab was flooded. The progress of brickwork has reached the level of the 19th floor.
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
October 2021
Section 1 - The vertical elements of the monolith are equipped at the level +12 100
Section 2 - Completed another slab at + 31,000
Section 3 - The slab continues to be poured at an elevation of +70,000. Brickwork is done on the 15th floor ⠀⠀
Section 4 - The progress of the brickwork has reached the 23rd floor level. Formwork is being set at +79,000
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
November 2021
Section 1 - Floor slab poured at elevation +18700
The vertical is now being filled at the same level.
Section 2 - The slab is poured, the vertical is poured at the mark + 40 000 (13th floor level)
Section 3 - A set of formwork is in progress, reinforcement of the floor slab at elevation +76 400 (level 24 floors)
Section 4 - Completed monolith.
The brickwork is almost complete.
Engineering communications are being laid (water, heating) - at the level of the 20th floor
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
December 2021
Section 1 - Reinforcement and concreting of the vertical continues at elevation +25000 (approximately 8th floor)
Section 2 - Floor slab is being performed at level + 46,000 (approximately 15th floor)
Section 3 - Reinforcement of vertical elements at elevation +79 600 (level 26 floor)
Section 4 - Roofing is in progress, an insulating layer is laid.
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
January 2022
Section 1 - The floor slab is being carried out at level + 31000 Section 2 - Reinforcement and concreting of the vertical at the level of + 52,000 is being carried out Section 3 - Reinforcing the roof parapet in progress Section 4 - Installation of windows at the level of the 17th floor continues
foto
foto
foto
foto
foto
foto
foto
February 2022
4 Section
- fully completed monolith
- the installation of window structures on the 1-2 floors is being completed
- electrical work is ongoing (lighting, emergency lighting, entrances to the apartment, low-jet networks) from the 3rd to the 25th floor
- the device of the fire system was completed from the 3rd to the 25th floor
- plumbing work is underway from the 3rd to the 25th floor.
3 section
- brick walls are being laid on floors 22-23
- completion of work on the boiler room on the roof and one of the parts of the parapet
- electrical work is being carried out (lighting, emergency lighting, entrances to the apartment, low-jet networks) from the 3rd to the 16th floor
- the device of the fire system is made on the 4th floor
5 Section
- Reinforcement and concreting of vertical elements of the parking lot continues
2 Section
- Reinforcement and concreting of the vertical of the 18th floor continues
- Brick walls are being laid on the 7th floor
1 section
- Reinforcement and concreting of the floor slab of the 11th floor continues
foto
foto
foto
foto
foto
foto
foto
foto
foto