May 2020
24 piles were made for the house of section # 4 The pile frames of section 4 were taken to the construction site in full
foto
foto
foto
foto
foto
foto
foto
July 2020
(Русский) Закончены работы по устройству ограждения котлована 4 секции. Забито 110 из 158 свай секции 4. Начать работы по разработке котлована 3й секции. Планируется в течение 3-4 недель завоз и монтаж башенного крана 4 секции
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
August 2020
(Русский) Начаты работы по устройству свай секции 3 Завершено устройство бетонной подготовки для фундаментной плиты секции 4 Выполнено бетонирование плиты фундамента башенного крана # 1
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
September 2020
(Русский) Выполняются работы по армированию фундаментной плиты секции №4 Завершены работы по разработке котлована части подземного паркинга в створах секций №3 и №4 Выполнена щебеночная подготовка на секции №3 Завершено обустройство бетонной подготовки для фундаментной плиты №3 Завершено вязкую каркаса и обустройство опалубки фундаментной плиты секции №4 Осуществляется прием бетонной смеси в плиту фундамента секции №4, общим объемом 750 м³
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
October 2020
(Русский) Выполняются работы по армированию фундаментной плиты секции №4 Завершены работы по разработке котлована частей подземного паркинга в створах секций №3 и №4 Выполнено щебеночное подготовку на секции №3 Завершено обустройство бетонной подготовки для фундаментной плиты №3 Завершена вязка каркаса и обустройство опалубки фундаментной плиты секции №4 Осуществляется прием бетонной смеси в плиту фундамента секции №4, общим объемом 750 м³
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
November 2020
Section 2: Water lowering measures in the area of ​​the elevator pit have been completed Work has begun on the reinforcement of the foundation slab Section 3: Work is underway on the arrangement of vertical parking elements and a set of floor slabs Section 4: Work is underway on the arrangement of the floor slab of the 4th floor at the mark +8800
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
December 2020
Section 4 - the formwork of the 7th floor floor slab is being assembled at the mark +12100, ventilation units up to the mark +12 100 have been installed;
Section 3 - reinforcement of vertical elements of the 3rd floor is performed at the mark +5 500;
Section 2 - reinforcement of vertical parking elements is performed at the mark -3400;
Other works - concreting of the foundation slab of the parking lot outside the building spot of the sections was performed.
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
January 2021
SECTION 4 - reinforcement of vertical elements of the 8th floor is performed at the mark + 18 700, grinding of monolithic structures and preparation for brickwork of walls continues, works on arrangement of wall formwork of part of underground parking outside the spot of construction of sections are performed;
SECTION 3- reinforcement of vertical elements of the 5th floor at the mark +8 800 and dismantling of the formwork of the floor slab, ceiling height - 6 m
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
February 2021
Work has begun on laying the brick walls of section 3