  • Перша черга будівництва
2020
June
July
August
September
October
November
December
2021
January
February
March
April
May
June
June 2020
24 piles were made for the house of section # 4 The pile frames of section 4 were taken to the construction site in full
foto
foto
foto
foto
foto
foto
foto
July 2020
Закончены работы по устройству ограждения котлована 4 секции. Забито 110 из 158 свай секции 4. Начать работы по разработке котлована 3й секции. Планируется в течение 3-4 недель завоз и монтаж башенного крана 4 секции
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
August 2020
Начаты работы по устройству свай секции 3 Завершено устройство бетонной подготовки для фундаментной плиты секции 4 Выполнено бетонирование плиты фундамента башенного крана # 1
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
September 2020
Выполняются работы по армированию фундаментной плиты секции №4 Завершены работы по разработке котлована части подземного паркинга в створах секций №3 и №4 Выполнена щебеночная подготовка на секции №3 Завершено обустройство бетонной подготовки для фундаментной плиты №3 Завершено вязкую каркаса и обустройство опалубки фундаментной плиты секции №4 Осуществляется прием бетонной смеси в плиту фундамента секции №4, общим объемом 750 м³
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
October 2020
Выполняются работы по армированию фундаментной плиты секции №4 Завершены работы по разработке котлована частей подземного паркинга в створах секций №3 и №4 Выполнено щебеночное подготовку на секции №3 Завершено обустройство бетонной подготовки для фундаментной плиты №3 Завершена вязка каркаса и обустройство опалубки фундаментной плиты секции №4 Осуществляется прием бетонной смеси в плиту фундамента секции №4, общим объемом 750 м³
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
November 2020
Section 2: Water lowering measures in the area of ​​the elevator pit have been completed Work has begun on the reinforcement of the foundation slab Section 3: Work is underway on the arrangement of vertical parking elements and a set of floor slabs Section 4: Work is underway on the arrangement of the floor slab of the 4th floor at the mark +8800
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
December 2020
Section 4 - the formwork of the 7th floor floor slab is being assembled at the mark +12100, ventilation units up to the mark +12 100 have been installed;
Section 3 - reinforcement of vertical elements of the 3rd floor is performed at the mark +5 500;
Section 2 - reinforcement of vertical parking elements is performed at the mark -3400;
Other works - concreting of the foundation slab of the parking lot outside the building spot of the sections was performed.
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
January 2021
SECTION 4 - reinforcement of vertical elements of the 8th floor is performed at the mark + 18 700, grinding of monolithic structures and preparation for brickwork of walls continues, works on arrangement of wall formwork of part of underground parking outside the spot of construction of sections are performed;
SECTION 3- reinforcement of vertical elements of the 5th floor at the mark +8 800 and dismantling of the formwork of the floor slab, ceiling height - 6 m
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
February 2021
Work has begun on laying the brick walls of section 3
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
March 2021
Section 1. In March, work will begin on the development of the pit: the arrangement of the pile field, etc.
In 2 sections works on the device of reinforced concrete vertical elements of the atypical first floor are carried out. The term of performance of these works makes more than 3 weeks, after all height of a floor - 5600 mm. Also on this floor there is a built-in transformer substation
Section 3. Works on arrangement of vertical elements of the 8th floor are carried out
Section 4. Works on arrangement of a plate of overlapping of the 10th floor are carried out . Work on the installation of ventilation units, flight of stairs, platforms (production gap is 2 floors) is planned. Work is underway on the arrangement of external and internal walls and partitions on the 4th and 5th floors. From May 1, the process of arranging internal engineering networks will begin
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
April 2021
SECTION 1 - work begins on the arrangement of the foundation piles
SECTION 2 - a set of floor slabs at the mark +5500
SECTION 3 - vertical elements of the 9th floor at the mark +28 000
OTHER WORKS: Masonry work has begun in the basement. The level of the tower crane №2 is raised
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto
May 2021
Section 1 - completed work on the arrangement of foundation piles. The foundation for the tower crane has been prepared. Compacted soils under the foundation slab.
Section 2 - a set of floor slabs is made at the mark +8800 - office floor.
Section 3 - vertical elements are mounted at the mark +37 000. Work on masonry of external walls and partitions from the 3rd to the 6th floor inclusive continues.
Section 4 - a set of floor slabs is made at the mark of +46 000. Works on masonry of external walls and partitions from the 3rd to the 7th floor inclusive are carried out.
Other works: Work on masonry walls in the basement and on the technical floor has been completed.
foto
foto
foto
foto
June 2021
Section 1 - Concrete preparation for the foundation slab has been made. Reinforcement of the foundation slab begins.
Section 2 - A set of floor slabs at elevation +15 400 is in progress. Filling of vertical elements is continued at elevation +12 100
Section 3 — The floor slab is being concreted at elevation +43 000.
Section 4 - Concreting of vertical elements at elevation +49,000 is in progress. Progress in brickwork has reached the level of the 11th floor
We also remind that the third tower crane was installed on the construction site last month.
foto
foto
foto
foto
foto
foto
foto
foto
foto
foto