Venice of Kyiv welcomes spring. The nature of Rusanivka wakes up in the same way as decades ago, when the first construction began here. Since then, the architecture of the massif has changed, step by step it has crossed the border of centuries. And today, on the banks of the legendary canal, your modern and exemplary Rusaniv Residence is growing and approaching readiness.
We report on construction work:
The reinforced concrete foundation of the tower crane is being dismantled for the entrance to the underground parking
Section 1
- Installation of window structures is in progress
Section 2
- Installation of a ventilated façade continues
- Installation of water supply and sewerage risers has been completed
- Electrical wiring of lighting of common areas and fire alarm has been completed
Section 3
- Installation of the façade in the section continues
- Installation of elevators has been completed, commissioning is underway
- Finishing works are in progress: plastering of slopes of common areas and flights of stairs
Section 4
- Facade works are in progress
- Installation of heating radiators is being completed
- Laying tiles on flights of stairs
- A fire ventilation system is arranged
Section 5
- Brick work on the section has been completed