Хід будівництва у лютому 2024 року

There are days when we, Ukrainians, need even greater unity, motivation and inspiration to continue moving forward, to overcome common challenges, to believe that the result is not far off.

The good news is that the scale and meanings of Rusaniv Residence inspire everyone who works on the project. And we see the results every day. And every month we report on the progress in construction work:

The drilling rig performs work on the arrangement of the retaining wall of the entrance to the underground parking

Section 1

- Glazing at the level of the 18th floor is in progress

Section 2

- Installation of a ventilated façade has begun

- Electrical installation and plumbing works (wiring of communications) are in progress

- Laying of communication risers and window structures of technological openings from the 7th to the 25th floor is in progress

Section 3

- Facade works are in progress

- Installation of elevators continues

- Installation of fire valves has been completed

Section 4

- Facade works continue

- Interior finishing works are underway

- Installation of apartment heating devices is in progress

Section 5

- Bricklaying is nearing completion (basement; 5th floor)

- Installation of parapets on the terrace has been completed

- Completed brickwork decoration of ventilation ducts