Construction progress for September 2020

Works on reinforcement of the foundation slab of section №4 are performed

Works on development of the pit of underground parking parts in the sections цій3 and №4 have been completed

Crushed stone preparation was performed in section №3

The installation of concrete preparation for the foundation slab №3 has been completed

The binding of the frame and the arrangement of the formwork of the foundation slab of section №4 have been completed

Acceptance of concrete mix in a plate of the base of section №4, with a total volume of 750 m³ is carried out