Construction progress for October 2020

Section 4: works on arrangement of vertical elements of a technical floor are carried out;

Section 3: works on arrangement of vertical elements of parking are carried out;

Section 2: works on arrangement of piles are carried out (60% of piles are executed);

Other works: the foundation is being reinforced under the tower crane # 2; completed work on the removal of the collector # 3.

Completed works on the construction of a pit for underground parking near sections # 4, 3 and 2.